Partnering Resources for Federal Contractors
Directly actionable compliance tools: an interactive 35-day post-award checklist, answers to frequent partnering questions, and authoritative federal specifications.
Post-award partnering checklist
Follow these seven sequential steps immediately following award to ensure compliance with UFGS 01 30 00 Section 1.11.
Readiness Tracker
0% Complete1. Locate the partnering paragraph in your contract
Verify UFGS 01 30 00 §1.11 or FSC Annex 0200000 §2.3.3 and confirm whether Formal Partnering (with neutral facilitator) applies.
2. Retain a neutral third-party facilitator immediately
The initial session must occur within 35 calendar days of award and before physical on-site work begins. Retain OPAL Pacific early to lock in your date.
3. Reserve a mutually agreed off-base venue
Coordinate a full-day off-base conference facility in Guam (or regional hub) with audiovisual and breakout capability.
4. Confirm key stakeholder attendance
Secure attendance from the ROICC/FEAD construction managers, Designer of Record, prime PM and superintendent, and major subcontractor leaders.
5. Flow partnering requirements down to subcontractors
Incorporate mandatory partnering attendance and IRL escalation commitments into trade subcontracts. Contact OPAL Pacific to obtain tailored subcontract and joint-venture partnering clauses for your project.
6. Calendar follow-on sessions at 3-to-6-month intervals
Establish standing quarterly alignment sessions and team health assessment schedules for the duration of the contract performance period.
7. File session deliverables with official contract records
Ensure the signed Partnering Charter, Disputes Resolution Ladder, and Risk Register are submitted to the Contracting Officer and filed in eCMS.
Partnering compliance FAQs
Common questions regarding costs, authority, timelines, and attendance requirements under federal partnering specifications.
Who pays for partnering?
Does the Partnering Charter alter or modify my contract?
How soon after award must the initial session happen?
Who is required to attend the initial workshop?
What happens if an issue cannot be resolved in the field?
Can OPAL Pacific facilitate projects outside of Guam?
Authoritative references
Official government specifications, playbooks, and industry standard authorities governing federal construction partnering.
Federal Specifications & Policy
Need customized partnering clauses or workshop setup?
Our facilitation practice provides tailored subcontract flow-down language, complete agenda design, venue logistics, and charter documentation.
Contact Our Facilitation Practice →